IGB’s Commercial Operation Date announced

Commercial Operation Date (COD) of the Interconnector Greece-Bulgaria (IGB), which is expected to deliver 1 billion cubic meters of gas per year from Azerbaijan to Bulgaria is set for the second quarter of 2021, executive director of ICGB project company Teodora Georgieva told Trend.
She noted that the interconnector’s construction was commenced on Oct.28, 2019 and the duration is 18 months.
As for the current status of the project, Georgieva said the first pipe yard for acceptance and storage of line pipes and construction camp on Bulgarian territory is ready and the second pipe yard in Bulgaria is in preparation.
"Survey and clearance of the Right of Way strip in Bulgaria is ongoing (7.5 km RoW is cleaned). Until Feb.26, 2020, around 1,224 of pipes have been delivered in the pipe yard in Bulgaria with cumulative length of 17,682 meters," said the executive director.
She pointed out that the main tenders are already finalized and the main contracts are assigned.
"We do not expect tenders of such scale as the previous EPC and the Line Pipe Supply tender," Georgieva explained.
The Interconnector Greece-Bulgaria project envisages a two-stage development.
In the first stage, the pipeline capacity will be 3 billion cubic meters of gas, of which 2.7 billion cubic meters will be offered for the long-term market, the remaining share of 0.3 billion cubic meters in the short term.
In a second phase, also depending on the evolution of the market, the capacity of the pipeline can be increased to 5.3 billion cubic meters of gas thanks to the addition of a compression station: 4.5 billion cubic meters of gas 0.5 billion cubic meters of short-term gas will be offered for long-term products.
Latest news
Latest newsBulgaria Intercepts Boat Carrying 35 Migrants in the Black Sea
27.Nov.2026
Pro-European Protests Continue in Georgia as Opposition Calls for Large-Scale March in Tbilisi on November 28
27.Nov.2026
Bulgaria Strengthens Its Air Defence: Sofia to Acquire Five Additional IRIS-T SLM Systems for €925.9 Million
26.Nov.2026
Armenia Seeks to Assume Full Responsibility for Border Security as Yerevan Strengthens National Sovereignty
26.Nov.2026
Russian State Duma Approves Increase in Defence Spending for 2027: One in Every Three Rubles to Go Towards the War
25.Nov.2026
Armenia Revises Its Constitution: Pashinyan Proposes a New Stage of State Development and a Peace Agenda
25.Nov.2026
EU Presents 22nd Sanctions Package Against Russia: Restrictions to Target Banks, Shadow Fleet and Participation in European Sports
24.Nov.2026
Latvia and Armenia: Cautious Support for a European Path
24.Nov.2026
Two Commercial Vessels Attacked in the Black Sea off Bulgaria
23.Nov.2026
EU Allocates Another €1 Billion to Ukraine: European Military Support Takes on a Long-Term Dimension
22.Nov.2026
Europe Prepares a Military Mission for Ukraine: 2800 Troops Rehearse Post-War Deployment Scenarios
21.Nov.2026
Russian Missiles and a Drone Fall on Polish Territory: NATO Faces New Threats on Its Eastern Flank
21.Nov.2026
Russia Strikes Kyiv Bridges Following Ukraine’s Attack on the Crimean Bridge: Transport Infrastructure Becomes a New Front in the Escalation
20.Nov.2026
The "Coalition of the Willing" Discusses Security Guarantees and Continued Support for Kyiv
19.Nov.2026
Tanker Sinks off Bulgaria After Being Hit Four Times: All 19 Crew Members Rescued
18.Nov.2026

28 Nov 2026